Kempton Park to Richards Bay at forty
A 96-tonne transformer left this yard at nine on a Thursday night and reached the Bay on Sunday morning. Three nights, two provincial permits, an escort in front and one behind, and a man on foot at every bridge on the N2 watching the clearance. Average speed over the whole run was under forty. Abnormal load work is mostly paperwork and patience. The permit takes ten working days if the application is clean and three weeks if it is not. We do the route survey before we apply, because the department will happily approve a route we cannot actually drive, and then it is our problem at two in the morning outside Piet Retief. Send us the drawing early and we will tell you honestly whether the date you want is possible.